Flamstead Heritage Project Update

Following the all the hard work of Andrew Lambourne and all of the volunteers and workers, the first phase of the project is nearing completion. With our fantastic church now fully open again, we are looking forward to the next phase of the project. This will involve...

Reassembling the medieval roof

After 7 months of painstaking work during the course of this year – carefully taking the failing roof apart, updating the drawings and repair specifications, ordering timber in good time to beat the supply shortages, fabricating the new parts – the roof of...

Uncovering the 1960s cover-ups

Now that our scaffolding is complete, and the weatherproof roofing installed, we’ve started to uncover the areas needing restoration work. These were last worked on in the 1960s: the copper roof replaced the original lead roof in 1961, and the Glass Reinforced...